The Department of Management Services is a year behind on replacing Florida’s statewide government network. The contract it put back on the street in August is one the agency’s own consultants priced at $75.9 million more over a decade than the version it dropped in April.
The procurement is MyFloridaNet-3, the successor to the private network that carries data, internet, and cloud traffic for state agencies, counties, cities, school districts, universities, libraries, and eligible nonprofits. DMS estimates annual spend on the contract at about $60 million.
The initial term is seven years, with a seven-year renewal available. On the schools and libraries side alone, DMS told the federal E-Rate program in an Aug. 24 filing that the contract would serve 7,876 schools, 818 libraries, and 671 non-instructional facilities.
L3Harris Technologies has run the current network, MyFloridaNet-2, since Harris Corp. won a $700 million contract in October 2016, a seven-year base with seven one-year options. DMS extended that deal for five more years in 2023. The network connects more than 4,100 sites.
DMS first went to market for MFN-3 on June 3, 2025, as ITN No. DMS-24/25-260. Replies came in Sept. 22, 2025. The agency’s timeline, as last amended that month, called for a notice of intent to award on June 15, 2026, and a signed contract on Oct. 7, 2026.
On April 27, 2026, seven weeks before the award date, DMS posted a one-page Notice to Reject All Replies. The notice gives no reason. It says the Department “intends to reissue a competitive solicitation.”
The reissue, ITN No. DMS-26/27-025, went up Aug. 24. Replies are due Dec. 7. Section 5.1 of the ITN reserves the Department’s right to reject all replies and reissue the solicitation. The new timeline puts the notice of intent to award at July 6, 2027, and contract execution at Oct. 1, 2027. Both dates fall after the next Governor takes office in January. At the $60 million a year DMS estimates, each month the award slips is roughly $5 million in spending under the existing MFN-2 contract.
The 2025 version bought “MyFloridaNet-3 Core Services” only. It split off the last mile, the circuits that run from the state backbone into each site, into a separate contract with what it called Transport Services Providers. Under that version, “DMS will contract directly with Transport Services.” The core vendor had to be ready for those providers’ connections within 180 days of award and would manage them day to day. Its Statement of Work read: “DMS requires an Enterprise solution provided by a single Core Services Provider managing the Transport Services Providers.”
The 2026 version folds the last mile back into a single award. Its Statement of Work covers MFN-3 Services “including core and last mile.” The corresponding sentence now reads: “DMS requires an Enterprise solution provided by a single Services provider managing existing telco partnerships for local loop, where required.” That is the model MFN-2 runs on today.
State law, Section 287.0571, requires a business case before an outsourcing of this size. DMS attached its MFN-3 business case to both solicitations. The study is dated Sept. 6, 2024, and was prepared for DMS by the consulting firm ISF and the telecommunications firm Skyline.
The consultants modeled two options over 10 years. A single-award, vendor-owned and vendor-managed network, the current approach, came in at about $68.7 million a year and $687 million over the decade. A multi-award model that carves out the last mile came in at $61.1 million a year and $611 million.
The business case calls the multi-award option “the lowest cost option” and describes the gap as “an annual ~$7.6M cost avoidance.” Both models exclude transition costs.
The estimate rests on data from Maryland, which runs a multi-award last-mile contract. Across 68 sites in a Maryland project, picking the lowest-cost vendor for each circuit produced a median cost avoidance of 44% and an average of 39% compared with awarding every site to one vendor. After assuming the core vendor would add a 20% management fee to every circuit, the average savings held at 25%.
The consultants wrote that Florida’s market is more competitive than Maryland’s. In Maryland, 16% of sites had only one serviceable vendor. The Orlando and Miami markets each have at least six fiber ISPs.
Item 8 on the business case’s list of recommended contract improvements reads: “Consider unbundling core and last-mile services to encourage competition among providers.” The study also recommended making the state the customer of record for last-mile circuits, so the physical connections survive a future change of backbone vendors.
Neither is in the live ITN. The live ITN adopts other business case recommendations: tighter service-level agreements, state-directed security configurations, and review-and-approval language over the prime’s local loop provider choices. The business case states that under the current model, “the MFN vendor has the ultimate authority in selecting last mile providers for each of the MFN sites.”
In the new ITN’s scoring table, Attachment M, the largest technical category is “Migration from MFN-2 to MFN-3,” worth 750 points. The migration sections of the Statement of Work ask bidders for site inventories, knowledge transfer, network operations center transition, and connection-by-connection cutover plans for the MFN-2 network, which L3Harris operates.
The ITN as posted in August said the evaluation ran on 5,000 points, 3,000 technical and 2,000 cost. Attachment M added up to 6,885. Two bidders asked about the discrepancy. In an Oct. 20 addendum, DMS revised the ITN to 6,885 points: 4,175 technical and 2,710 for price.
All 2,710 price points ride on E-Rate eligible pricing, the federally discounted rates for schools and libraries. The ITN calls E-Rate eligible cost “the most heavily weighted component of the bid evaluation.” In the 2025 version, E-Rate pricing was worth 1,500 points, with another 500 on site inventory pricing.
L3Harris’s 2023 extension announcement cites the network’s E-Rate support and the “assigned Florida E-Rate Coordinators” who file the paperwork so school systems and libraries receive discounted service without issuing new requests for proposal.
Sean Gellis, a former DMS Chief of Staff who writes on state contracting at FloridaProcurements.com, wrote about L3Harris’s position when the first ITN was posted in June 2025. L3Harris, he wrote, enters “with nearly a decade of institutional knowledge, established relationships, and deep integration with Florida’s current telecommunications infrastructure.”
He called it “a classic procurement dilemma: How do you maintain the benefits of proven, stable infrastructure while ensuring competitive pricing and continued innovation?”
The public opening for the 2026 ITN is Dec. 7 at 3 p.m.DMS plans to evaluate from Jan. 4 to Feb. 12, 2027, and negotiate from March 1 to June 25, 2027.
—